Taking possession: the inspection to do before you accept the keys

6 min read · Last verified

In short

Before accepting possession, verify the occupancy certificate covers your building, measure the flat against the carpet area in the agreement, check the specification against the agreement schedule, test every fitting and service, and record all defects in writing and have them acknowledged before you take keys or pay the final instalment.

Key facts

Your leverage
The unpaid final instalment
Verify first
Occupancy certificate covering your building
Measure
Carpet area against the agreement figure
Document
Every defect, in writing, acknowledged
Collect
Full document set including plans and receipts

Handover feels like a formality after years of waiting, and it is treated as one by most buyers. It is in fact the last moment at which you have real leverage, because the final instalment has not yet been paid.

An hour of proper inspection here is worth more than any amount of correspondence afterwards.

Before you go: the documents

Establish the paperwork position before the inspection, because one of these can stop the process.

  • The occupancy certificate — confirm it exists and covers your specific building and tower.
  • Your agreement, so you can check carpet area and specification against it.
  • The approved plan for your unit.
  • The full payment record, so the final figure can be reconciled.

Measure the flat

Take a measure and check the carpet area against the figure in the agreement. This is rarely done and occasionally decisive.

If there is a shortfall beyond the tolerance the agreement permits, the adjustment mechanism is triggered — and it is far easier to raise before you take possession than after.

Check the specification against the schedule

The agreement contains a specification schedule. Walk the flat with it and check what was actually installed against what was promised — flooring, fittings, sanitaryware, doors, windows, electricals.

The show flat is not the standard; the schedule is. Where they differ, the schedule governs.

Test everything that has a function

Nothing here requires expertise. It requires patience and a systematic route through the flat.

  • Run every tap and check drainage in every outlet.
  • Flush every WC, and check for leaks under sinks and around fittings.
  • Switch every light and socket; test the distribution board.
  • Open and close every door and window, and check locks and handles.
  • Look for damp, particularly on external walls, around windows and in bathrooms.
  • Check floor level and tile finish, and tap tiles for hollowness.
  • Check the balcony railing height and fixing.
  • Confirm water pressure at the top of the range you would use.

Record defects properly

A verbal list is worth nothing three weeks later. Write every defect down, photograph each one with something for scale, and have the list acknowledged in writing by the developer's representative.

Agree a timeline for rectification and record it in the same document. A snag list without a date is an aspiration.

Understand the defect liability position

RERA provides for a defect liability period after handover, during which structural defects and defects in workmanship are the developer's responsibility to rectify.

Know what that period is for your purchase and when it starts. Report defects within it, in writing, and keep the correspondence.

Collect the full document set

You will need these for the society, for your lender, for property tax and eventually for your buyer.

  • Registered agreement for sale.
  • Possession letter.
  • Occupancy certificate.
  • Approved plan for the unit.
  • All payment receipts and the final statement.
  • Warranty documents for anything installed.
  • Details of the maintenance arrangement and what your advance covers.

Common questions

Should I take possession without an occupancy certificate?

Ask why it has not been issued before you accept keys. Occupation without one carries lending, resale and in serious cases enforcement risk, and handover is when you have the most leverage to press for it.

What is a snag list?

The written record of defects identified at handover. It should be photographed, acknowledged in writing by the developer, and carry an agreed rectification timeline.

What if the carpet area is smaller than the agreement says?

The agreement will specify a tolerance and an adjustment mechanism. Measure at handover and raise it then — it is much harder to pursue after you have taken possession and paid in full.

How long is the developer responsible for defects?

RERA provides a defect liability period after handover covering structural defects and defects in workmanship. Confirm the period applicable to your purchase, and report anything you find in writing within it.